Belgium orders Google to halt data center work over missing permit

This aerial photograph shows the construction site of a Google data center in Farciennes, on Nov. 27, 2026. (AFP Photo)
Photo
BigPhoto
This aerial photograph shows the construction site of a Google data center in Farciennes, on Nov. 27, 2026. (AFP Photo)
November 28, 2026 11:23 AM GMT+03:00

Belgian authorities have ordered Google to suspend construction of a data center on a former mining site in Wallonia, southern Belgium, because of a lack of proper planning permission, with inspectors delivering a stop-work order on Thursday, a regional official told Agence France-Presse (AFP) Friday.

"We have identified a major offence: the illegal construction of a building covering three hectares," or 7.4 acres, said Nicolas Yernaux, spokesperson for the Wallonia regional authorities.

The order at the former mining site covering some 50 hectares (124 acres) in total comes after NGO Greenpeace accused Google of carrying on construction despite lacking the correct permits.

The Google logo appears on a smartphone and a laptop screen in Frankfurt am Main, Germany, May 19, 2026. (AFP Photo)
The Google logo appears on a smartphone and a laptop screen in Frankfurt am Main, Germany, May 19, 2026. (AFP Photo)

River cooling plan sparks dispute

The mammoth project has been locked in legal litigation for months after Google applied to amend the terms of its planning permission.

The application sought to allow a cooling system for the facilities using water drawn from the nearby River Sambre, whereas the initial project had envisaged air cooling.

The move stirred local opposition as severe droughts since spring exacerbated fears about tapping the river, and regional officials refused the application over the summer.

Google has challenged that decision in court and a hearing is scheduled for January.

Construction continues at the Google data center site in Farciennes, Belgium, seen from the air, Nov. 27, 2026. (AFP Photo)
Construction continues at the Google data center site in Farciennes, Belgium, seen from the air, Nov. 27, 2026. (AFP Photo)

Drone footage shows ongoing work

But a report this week by Greenpeace Belgium said that drone footage showed work was still progressing in the meantime.

"The tech giant is currently continuing its work, even though in August the latest version of its planning permission to build this data center was revoked," the environmental group said.

"The climate crisis will only intensify in our region. Against this backdrop, the construction of energy-guzzling behemoths cannot be allowed to go unnoticed."

Wider pushback across Europe

The legal row over the Belgian data center is the latest confronting Google in Europe as tech giants push to build data centers to support the artificial Intelligence boom.

In October, Finnish authorities ordered work on two Google data center sites in the country to be halted until mandatory environmental impact assessments could be completed.